Production Lighting EICRs

Jan 10, 2023

Why inspect electrical systems?

Most of us know that we should have electrical systems inspected, but many people don’t know why. The following explains why we do them on theatrical (often called “production”) lighting systems and what we’re looking for. 

 

Any electrical system in a place of entertainment should be regularly inspected and tested.

Along with safety, this will be both to satisfy the requirements of the Electricity at Work Regulations and the insurer. In addition, it is very likely that the local authority will require regular inspections as a condition of their licence to operate. 


What is an EICR?

The formal report outputted as a result of the electrical inspection and testing is the Electrical Installation Condition Report (EICR). Detailing the safety and overall condition of the electrical installations and fittings at the establishment, it will outline if the electrical installation is in satisfactory condition or if it needs immediate or planned maintenance. An EICR can be carried out on a full installation or a single circuit within that system. It is crucial for the client and contractor to have a clear understanding of what will be done. As an example, while unlikely, it would be perfectly reasonable for the agreed scope to define the EICR as an

inspection and test of the circuit that supplies a single 15A socket located upstage left. Usually, the scope will determine the areas the inspection will cover and the agreed sampling approach to be taken.


There will almost always be limitations in addition to the agreed scope of work. Some limitations will be agreed between the client and the contractor.

An agreed limitation may be where removing a socket to physically check the connections may cause significant damage to the surrounding plasterwork, which would be costly to correct. The client would be asked to agree that the physical inspection of terminals couldn’t be carried out due to the risk of damage to the décor.


Operational limitations are common. The scope may define that the socket, located upstage left, is the only thing to be inspected. However, if the inspector finds that a 1000 kg item of a set has been stored in front of the socket, they will not be able to carry out that part of their agreed operation.


Inspecting entertainment venues

It’s advised in Guidance Note 3, which accompanies the IET Wiring Regs, that places of entertainment are formally inspected and tested every three years. This is in addition to a thorough but less invasive check being performed annually. Therefore, the annual check must be documented.

 

Many venues opt to have a third of their system inspected every year. This means that degradation or faults have a better chance of being spotted early and can satisfy the requirement for the documented annual check (if this is included in the agreed scope).

 

Whether the system is a couple of Strand Act6 dimmer packs and an 18-way, homemade patch panel or 1056+ ways of ETC Sensor 3 with all the distribution, hot power, and associated control, the purpose of an inspection is the same - to ensure that it is fit for continued use in the manner it was designed and, most importantly, to ensure that it is safe.


EICR – inspecting production lighting systems

Step 1 – Show everything in operation

The first step is to ask the person responsible for the system to show everything in operation. This gives them a chance to mention things that may not be working correctly or other things they may have noticed (an occasional smell of burning fish is never a good sign!).


Step 2 – Walk the system

We always walk the system to get a feel for what is where and the general condition. For example, a system with bent trunking lids and bits of forgotten old lanterns dumped across the walkways may not have a particularly gentle team using it. If there are no circuit identification markings, we ask for a layout drawing. Ideally, all systems should have the original design information available. If this is provided, we will look at it to see if the designer has made any notes that future inspectors would need.

 

Step 3 – Consider the supply

The next step would be to consider the supply to the building, the main electrical connections, and earthing arrangements. This would include checking the bonds to the incoming services (gas, water, heating), which is why we often ask for access to the boiler room.

 

With the origin dealt with, we start to look at the parts of the system directly associated with the production lighting. 


Step 4 – The distribution and circuits

First, we isolate and lock off the power to the systems and then, having proven that there is no power, we start looking in detail. There are checklists that we follow which include, but are not restricted to the following:


1. Carrying out physical inspections of assemblies to make sure they are mechanically sound.

2. Inspecting connections, ensuring they are tight enough and the cables have been correctly terminated. 

3. Considering the cable sizes and the ratings of the breakers used. The general assembly of the system is looked at, and where possible, we consider the number of cables within the containment (trunking). 

4. Looking for Surge Protection or other safety devices. In our view, surge was a sensible addition to the IET Wiring Regulations, especially when the value of some of the equipment is considered.

5. Testing with the power off to measure circuits agreed upon in advance. This allows us to check that sockets are correctly wired and that the cables are in good condition. If the circuits are part of a patch, we inspect the patch for wear and open the connectors in line with the agreed spec.

6. Opening and inspecting outlets, facility panels, and end boxes of internally wired bars while the power is off. 

7. Examining devices, accessories and switches and ensuring that they function correctly.

8. Assessing the suitability of fire prevention, suppression and blocking measures.

9. Cleaning the dimming and distribution equipment, where possible. Dimmers that have fans often end up with a lot of dust and dirt within and so we like to, at the very least, vacuum the filters and the insides of the enclosures. Convection-cooled enclosures in the west end have a very noticeably black and slightly sticky grime within.

 

With all the inspections and tests that can be done with power off complete, we reassemble the equipment. When we open things up or unplug patch cables, we make careful notes of where things are so that they are returned exactly as we found them. 

 

Live tests are performed with measured values checked against tables and manufacturer’s data. In addition, we test RCDs and other safety devices and make sure that the equipment is functioning correctly. 

 

With the system operating again, we like the person responsible to check everything is functioning as expected. While we do all we can to ensure that mistakes don’t happen, a seasoned eye will be more likely to spot anything awry. 

 

Step 5 – EICR outcomes – Satisfactory or Unsatisfactory

The outcome of an EICR will be “Satisfactory” or “Unsatisfactory”. This will depend upon what has been found and the severity. This is based on codes C1, C2, C3 and FI. Codes are given to everything the inspector observes that are not in line with the appropriate issue of the IET Wiring Regulations and the subsequent amendments.

 

  • C1 coding indicates an immediate risk of shock or fire; as inspectors, we can never leave this. For example, if a consumer blank is missing, we may fit one (if we have a suitable one) or create a robust temporary barrier. If we find that cables are dangerously overloaded, we may be forced to lock off the affected part of the system and give the key to the person responsible. In either case, a written report will be provided.

 

  • C2 coding can be viewed as something that could cause danger if another thing happens. For example, if an RCD doesn’t work, the circuit will still operate, but if there is an earth fault in a portable item of equipment, this could result in injury.


  • C3 tends to be given to items that are not right but not necessarily electrically dangerous. An example is the lack of a sign indicating that there are wiring colours to two versions of the IET Wiring Regulations within an enclosure. 

 

  • FI is used when the inspector cannot state whether something is dangerous. This could be that they didn’t have access to a particular area of the system or that tests proved inconclusive. At this point, the inspector may state that they couldn’t say with certainty that there was no potential for a fault to be present. As a result, a Further Investigation of the matter is necessary.

 

A C1 that cannot be corrected on-site except by shutting off the power will always be “Unsatisfactory”. This is also true of any system where a C2 or an FI has been given.

 

If there are C3s given, it may be appropriate for the inspector to conclude a “Satisfactory” outcome. This will depend on the quantity of C3s and the inspector’s opinion. An example could be where technically, an installation put together in 1958 is still as it was on the day of completion. It may be acceptable according to the standards in place at the time. Still, it is unlikely to be given a satisfactory outcome due to many factors we are now aware of, use of rewireable fuses (in certain circumstances), lack of RCD protection, etc.).

 

EICR – recording and photographing

Ideally, all items noted in our inspections will have been carefully recorded, and for larger systems, wherever possible, at least one clear photograph will have been taken. This attention to detail helps the person responsible identify what may need correcting and removes doubt. It will also prove invaluable when fixing the issues as the person tasked will be able to see what, in the inspector’s view, was wrong.

 

Get in touch

Please do contact me if you have any queries about this piece. It is intended to be lightly informative at a user level, and so some things have been brushed over. However, if you feel I have missed an important point, please let me know.

14 Aug, 2023
Our mobile system Our system is flexible and allows us to work at large scale very easily to any required spec’. We can work on any temporary power system from a single power source with one socket upwards. It’s the larger jobs where things really come into their own and where the data feedback, and efficiency of what we do, come to the fore. We use a mobile device tool to capture information from the field. The raw data is transferred to a highly secure service provider, meaning the information is safe as soon as it is captured and uploaded. Any changes that are required to the data (such as if someone realises that they have entered a circuit description incorrectly) are tracked and time stamped. Information gathering and data clarity Multiple images are taken as we carry out our inspections and tests. These can provide the client with clarity or enhanced information if we have identified something that should be reported. Any things we feel are appropriate to flag are immediately made available to our client. We tend to use an online portal for convenience and efficiency, which is connected directly to our site gathered data. This portal displays the values we have measured, the matter that the inspector believes to require flagging and all the images we have taken of that part of the electrical system. If we can make a problem go away, we always try to. Things like a breaker being left at an incorrect setting or a loose lug can be quickly attended to. We always ensure that the appropriate people know what we have done. On-site documentation review During our time on site, we regularly review the test documentation that our teams are submitting. From questioning values that don’t quite “feel” right to the clarification that a system has been put together in the way described, the second eye over the data is an integral part of our process. Test documents collated With all information reviewed, we collate all the test documents. We also provide schematics giving clear “as built” drawings of the systems we have visited. This is supplied as a pack to the client electronically, usually while we are still on site. A flexible, scalable solution The next time you wonder if there is an easier way of testing a temporary power system when time is tight, and the number of systems is large, we can very quickly and easily provide a solution. Much better than trying to fill in paper documents in the wind and rain. Let us know your requirements, and we can devise the fastest way of considering the equipment that you are installing. Your headache of trying to get the testing done is one we are happy to take away.
By Hugh Percival 17 Mar, 2023
HPES – our background
By Hugh Percival 14 Feb, 2023
Bespoke projects for mission critical systems
22 Nov, 2022
Can you just do a quick sign-off for us before tomorrow?
08 Nov, 2022
Why are Central Battery Systems so important for the upcoming panto season?
By Hugh Percival 11 Oct, 2022
So what does a ''day in the life of'' HPES look like while we are working outdoor events? Here is a light-hearted, but we hope an informative introduction revealing a typical day getting power systems ready for a large outdoor sporting event in Scotland earlier this year.
By Hugh Percival 05 Oct, 2022
Every year at HPES Technical Solutions, we spend a significant amount of time in regional and West End Theatres. Because so many theatres know our thoughts and feelings on all things theatrical, we are often asked, “who are some of the other theatrical electrical contractors within the industry, and who would you recommend?” So, here are our thoughts.
By Hugh Percival 10 May, 2022
Power Quality Measurement for an new client - and new skills for the team
17 Mar, 2022
Training to keep up to date with Surge Protection Devices
08 Mar, 2022
Successful power quality management for a new data centre
More Posts
Share by: